The project generally consists of a new detention center totaling approximately 57,700 SF. The project
is Type II-B construction, Group I-3 and Group B occupancy. Construction includes concrete and brick
veneer masonry construction with steel framing, interior CMU partitions, TPO roofing, architectural
casework, food service equipment, detention equipment, security electronics, and finishes typically
associated with a new detention center. The Project includes a kitchen, laundry, open-air vehicle sally
port, intake/ booking, Medical Suite, and a Magistrate Suite. Each housing unit will have access to an
open-air rec yard surrounded by concrete block. All cells within the housing units will be steel detention
cells. All housing units to be monitored by indirect supervision from a central elevated control room.
Sitework includes stormwater management, sidewalks, parking lots, grading, and fencing/ gates.
Mechanical work includes ductwork, plumbing, sprinkler system, smoke control system, controls, and
roof top units. Electrical work includes panelboards, lighting fixtures, fire alarm, emergency generator,
power, technology wiring and infrastructure; and security systems (cameras, intercoms, duress, door
controls, and touchscreens).